RAYNHAM HIGHWAY Construction Project Update

Notice

RAYNHAM HIGHWAY Construction Project Update

Mill Street Bridge project schedule:  EVERSOUCE will begin the gas main relocation on 9/5/23

with an estimated 3 weeks duration. Road closure maybe intermittent. The contract was awarded

in May 2023. Tree cutting was completed in August and utility relocation is in process.

 Construction begins in September through late November.